SamTruelove published Bookham water main to be replaced causing eight months of road...

A £800,000 water main project due to start next week will last eight months and affect nine roads in Bookham. Sutton and East Surrey Water is to replace 2.7km of old cast iron water mains with new, tougher plastic pipes that are less prone to bursts and leaks.The scheme aims to protect customers' drinking water supplies in parts of Bookham and starts on Monday (November 28).Apart from a break over the Christmas and New Year period, works will continue until July 2017.READ MORE: Little...

Bookham water main to be replaced causing eight months of road...



from Surrey Mirror All Content Feed http://www.surreymirror.co.uk/bookham-water-main-to-be-replaced-causing-eight-months-of-road-works/story-29921616-detail/story.html